Construction of site facilities

One ​​of the main activities of Contact International is the construction of on-site facilities in oil and gas fields. The technology for performing work on a rotational basis at remote sites, in areas with poorly developed infrastructure, has been developed. The company has extensive experience in mobilizing construction machinery, equipment and materials over long distances in a short time to carry out construction and installation work.

The company's production capacity allows us to mobilize and concentrate the required amount of personnel, equipment and material resources at the facilities to achieve the required deadlines for completing the work.

In the process of constructing facilities, Contact International relies on the modern level of production and new approaches to ensuring environmental safety.

Our projects:

Boosting pumping station for the West Ust-Balykskoye field.

Construction Booster pump station with linear pipelines for transporting oil and gas. Built in 9 months.



Designed installation capacity:

-for oil 2.5 thousand tons/day
-6.3 thousand m3 per day for liquid
-180 thousand m3 per day for gas

GTPP for the Taylakovskoye field. Power – 36 MW.

Average construction duration -11 months
The duration of operation of the main components without major repairs is 100-130 thousand hours.
Efficiency when recycling gases is up to 93%.
Efficiency 51%.





Infrastructure objects

Building to accommodate rotational personnel for 60 people in the area of ​​booster station 2 of the Taylakovskoye field.

The average construction duration is 10 months.

Sports and recreation complex in the OBP area of ​​the Southern part of the Priobskoye field.

Average construction duration -5 months.

Canteen in the BPO area of ​​the southern part of the Priobskoye field.

The average construction duration is 3 months.

Canteen in the BSO-2 area of ​​the southern part of the Priobskoye field.

Average construction duration -2 months.

Canteen in the BSO area of ​​the northeastern part of the Palyanovskaya area of ​​the Krasnoleninskoye field.

Average construction duration -2 months.